Gather Here. Go Far

With locations in Tahlequah, Muskogee and Broken Arrow, NSU is Oklahoma’s immersive learning institution. Choose from in-person, blended or online learning options.

Scholarships

NSU is committed to assisting students in applying and earning scholarships. Whether you are an incoming freshman or a continuing/returning student, NSU has a wide variety of scholarship options for students to choose from.

Clubs and Organizations

From networking to leadership opportunities, NSU’s over 80 clubs and organizations allow our students to build lasting relationships while getting the full college experience.

Transfer Students

Whether you’re an incoming or current transfer student, NSU’s transfer advisors are available to assist you with transcript evaluation, information on degree programs and support services. NSU is where You Belong.

Graduate College

Whether transitioning to graduate school or returning to higher education, NSU’s graduate college is your next step. Choose from over 25 master's degrees and several certificate programs.

Cabinet Meeting Notes July 16, 2013

Cabinet Meeting Notes July 16, 2013

Tuesday, July 16, 2013 | 9:00 a.m. | President's Office Conference Room
Cabinet was called to order by Provost Rugg at 9:00 a.m.
Members present: Dr. Bill Rugg, Mr. Tim Foutch, Mr. David Koehn, Mr. Ben Hardcastle, and Dr. Laura Boren
Members not present: Dr. Steve Turner

Capital Project Update

Mr. Foutch reported that all projects are progressing as planned. See below for a detailed list of activities.

Multi Purpose Event Center
. Exterior brick complete on east face of building
. Restroom tile install ongoing
. Paint and ceiling grid ongoing in Athletic office area
. All restroom fixtures have been delivered to the distributor, available for site delivery as needed
. Community building footings complete
. Glass framing is underway at main entry
. Slab pour for Community building scheduled for week of 07/15/13

Fitness Center Renovation
. Final building design established
. Civil package bids being developed
. NOPFA installing gas line on west side of building

Low Vision Clinic
. Finalizing building permit documentation
. Demolition phase scheduled to begin week of 7/15/13

Green and White Room renovation
. Interior paint underway, ceiling grid and trim to follow

Occupational Therapy Build Out
. Design documents scheduled for completion 08/02/13
. Bids scheduled for release mid August

Library Shell Renovation
. Roof material on site
. Roof work scheduled to begin week of 7/15/13
. Working with departments regarding relocation of equipment and furnishings
. Flooring materials scheduled for shipment 08/02/13

Special Services Remodel
. Roof construction scheduled to begin week of 7/15/13
. Magnum Construction is apparent low bidder for restrooms, windows and paint, bid response review underway

Summer Bathroom Remodels
. Administration bathroom remodel work scheduled to begin the week of July 22
. Bid packages for Haskell Hall scheduled for release July 25

Willis Parking Lot
. Engineering services under review
. Bid documents being developed

Enrollment Update

Dr. Laura Boren reported that efforts continue to increase enrollment numbers. Cabinet members discussed the need to pull together a marketing campaign to help push enrollment. Enrollment Management staff will reach out to Smart Choice schools for contacting perspective students.

Announcements

Follow-Up to Disney

Cabinet members discussed the need to follow-up with staff regarding the Disney Staff Development Training. Discussions will continue when all cabinet members are present.

The meeting was adjourned at 10:30 a.m.

Respectfully submitted,
Robin Hutchins